A number of in a single day work zones are deliberate on Interstate 95 from Quantico to Fredericksburg by means of Friday, July 22.
This text was written by InsideNoVa.com, a WTOP information companion, and republished with permission. Join the free InsideNoVa.com electronic mail subscription as we speak.
A number of in a single day work zones are deliberate on Interstate 95 from Quantico to Fredericksburg by means of Friday, July 22.
I-95 northbound and southbound will probably be decreased to 1 lane in a single day close to a number of interchanges between exit 148 (Quantico) for Specific Lanes building and exit 104 (Carmel Church) in Caroline County for operations of paving.
Crews from the 95 Specific Lanes Fredericksburg Extension challenge will start preparatory work to soundly erect and set up the bridge girders for the long run flyover bridge to Quantico. It is going to be considered one of three new Specific Lanes entry factors as a part of the challenge in Stafford County, the Virginia Division of Transportation mentioned in a information launch.
Between midnight and three am, crews will probably be required to cease all southbound site visitors on I-95 intermittently close to Quantico for as much as 30 minutes at a time.
Between every cease, congestion will probably be allowed to clear earlier than the following full site visitors cease. The Virginia State Police will help with site visitors management.
Nightly milling and paving operations will proceed on I-95 in each Caroline and Spotsylvania County, requiring twin lane closures.
From Tuesday, July 19, by means of early Thursday, July 21, the I-95 southbound ramps on the Exit 104 interchange will shut nightly at 10 p.m. to permit crews to pave, in accordance with the discharge.
Southbound vacationers searching for the exit 104 interchange will probably be rerouted to Exit 110 (Ladysmith) to Route 1 South to Route 207 (Rogers Clark Boulevard) and the Carmel Church space. Each the doorway and exit ramps will reopen at four:30 am
VDOT advises drivers with locations exterior of the Fredericksburg space to contemplate alternate routes to keep away from vital delays. Earlier than starting a visit, motorists are inspired to test 511Virginia.org for real-time updates on work zones and site visitors circumstances.
Street Work Forward: Southbound I-95 Closure and Rerouting Scheduled for August 2-5
To securely erect and set up bridge girders close to Quantico, crews will shut southbound I-95 every night time and divert all southbound site visitors to Route 1. Drivers will proceed south on Route 1 and can re-enter I-95 southbound at exit 143 (Garrisonville) in Stafford County.
Climate allowing, the closure and rerouting of I-95 southbound is scheduled for 3 nights starting Tuesday, August 2 by means of early Friday, August 5.
For extra info on this work zone, go to expresslanes.com.